Taseko Announces Fourth Quarter Production Update
For the fourth quarter of 2009, the Gibraltar Mine produced 17.3 million pounds of copper and 113 thousand pounds of molybdenum. For 2009, annual production was 70.3 million pounds of copper and 629 thousand pounds of molybdenum.
The fourth quarter production breakdown is as follows:
------------------------------------------------------------------------- October November December ------------------------------------------------------------------------- Mill Throughput (millions, tons) 1.1 1.1 1.0 ------------------------------------------------------------------------- Recoveries (%) 79.9 82.8 89.8 ------------------------------------------------------------------------- Production (millions, lbs) 4.8 5.7 6.8 -------------------------------------------------------------------------
The mine returned to steady state operating condition by November, following the geotechnical event in July.
Mr. Hallbauer continued, "We continue to make steady progress with construction activities at the mine. The tailings pumping system and in pit crushing and conveying system are near completion. Detailed design of the new coarse ore reclaim facility is in its final stages and construction is expected to begin in March. With these initiatives underway, we are on schedule to increase annual copper capacity to 115 million pounds by the end of 2010."
Russell Hallbauer President and CEO
No regulatory authority has approved or disapproved of the information contained in this news release.
Forward Looking Statements
This release includes certain statements that may be deemed "forward-looking statements". All statements in this release, other than statements of historical facts, that address future production, reserve potential, exploration drilling, exploitation activities and events or developments that the Company expects are forward-looking statements. Although the Company believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Factors that could cause actual results to differ materially from those in forward-looking statements include capital market conditions, commodities market prices, exploitation and exploration successes, lack of continuity of mineralization, continued availability of capital and financing, the ability to obtain and maintain required permits, including environmental, construction and mining permits and general economic, market or business conditions. Investors are cautioned that any such statements are not guarantees of future performance and that actual results or developments may differ materially from those projected in the forward-looking statements. For more information on the Company, Investors should review the Company's annual Form 40-F filing with the United States Securities and Exchange Commission or the Company's home jurisdiction filings at www.sedar.com.
SOURCE Taseko Mines Limited