Mass excavation nearly half complete; crews have removed more than 180,000 tons of soil, enough dirt to fill half of Joe Louis Arena
Foundation work to begin in late June; mass excavation, utility relocation and earth retention to be complete in July
DETROIT, June 10, 2015 /PRNewswire/ -- In just six short weeks since mass excavation began on the new Detroit Events Center site, crews have removed more than 225,000 cubic yards of soil to make way for the centerpiece of The District Detroit's Woodward Square neighborhood. The new arena will be home to the Detroit Red Wings, other sports and entertainment events, concerts, family shows and community functions. Crews working on site are nearly half of the way to removing an estimated 480,000 cubic yards of dirt for the Events Center bowl.
"Seeing the transformation that is taking place on this critical stretch of Woodward Avenue is exciting," said Steve Marquardt, Vice President of Olympia Development of Michigan. "We are working hard to create one of the world's premier urban environments, featuring a Detroit-fueled arena design that's great for fans and visitors, a neighborhood-friendly profile and active shops, offices and public spaces. The District Detroit will be a connector for the great things that are happening in our city."
Creating a Fan- and Neighborhood-friendly Arena
Excavation currently underway will create a dramatic arena bowl for fans and world-class seating options for guests at concerts, family shows and other events. Fans will also be able to enter the arena's concourse between upper and lower bowls at street-level, unlike traditional arenas that require patrons to scale steps to reach the concourse. Additionally, excavation will optimize the visual impact of the arena on the surrounding neighborhood, resulting in an overall height 20 percent lower than typical arenas.
"The new arena will set the standard for the things that make a fan experience unforgettable: proximity to the action, sight lines, amenities and technology. Fans are going to love this newer, personalized experience - it will be a very exciting place to be," said Tom Wilson, President of Olympia Entertainment. "Crews are hard at work on site, and we are making great progress on the arena bowl and the mixed-use buildings surrounding it."
Construction Moving Quickly, Featuring Detroit Firms
In addition to mass excavation, work currently taking place on site includes relocation of utilities, creating construction roadways and the placement of construction trailers. The next phase of work on site will include the placement of caissons, setting the foundation of the Events Center. That work is expected to begin in July.
"This is a once in a lifetime project in our hometown, built with Detroit businesses and by Detroit labor. There is real energy, excitement and pride coming from the crews at the construction site who are working hard to remove soil and dig the bowl of the new events center. It's a great feeling to be a part of the District Detroit project," said Kerlin Blaise, owner of Blaze Construction.
To date, the Detroit Downtown Development Authority has approved seven contracts for the project worth $85 million, of which, Detroit-based and -headquartered businesses have won more than 90 percent, or $78 million. Olympia Development of Michigan has set a target of at least 30 percent Detroit-based and -headquartered business participation in constructing the future home of the Detroit Red Wings. Olympia Development has also hosted more than half a dozen job fairs, where thousands of Detroiters and others have met with skilled trade unions; registered with the city's workforce agency, Detroit Employment Solutions; and accessed training and financial aid resources.
About the Detroit Events Center
Home to the Detroit Red Wings, other sports and entertainment events, concerts, family shows and community functions, the Detroit Events Center will feature a dramatic arena bowl, proximity to the action and great sight lines. Rich with the tradition of the Original Six Detroit Red Wings and Detroit's incredible musical heritage, the new Detroit Arena will also feature state-of-the-art technology and fan amenities. The Detroit Events Center will open in the fall of 2017, and it's going to deliver amazing experiences.
About The District Detroit
The District Detroit will be made up of a dynamic mix of sports and entertainment venues, including six world-class theatres and three multi-use sports venues – home to the Detroit Red Wings, the Detroit Tigers and the Detroit Lions. The District Detroit will also feature residential, office and retail developments that connect these venues into one contiguous, walkable area, where families, sports fans, entrepreneurs, job seekers, entertainment lovers and others who crave a vibrant urban setting can connect with each other and the city they love.
Construction of the arena and surrounding District is expected to generate at least $1.8 billion in total economic impact, 8,300 construction and construction-related jobs and 1,100 permanent jobs. More than $100 million in income from the Events Center project alone is expected for Detroit residents, with significant additional income to be created through future private development. Learn more at www.DistrictDetroit.com.
Photo - http://photos.prnewswire.com/prnh/20150611/222350
Photo - http://photos.prnewswire.com/prnh/20150611/222349
Logo - http://photos.prnewswire.com/prnh/20150611/222356LOGO
SOURCE Olympia Development of Michigan
WANT YOUR COMPANY'S NEWS FEATURED ON PRNEWSWIRE.COM?
Newsrooms &
Influencers
Digital Media
Outlets
Journalists
Opted In
Share this article