PPL Susquehanna Addressing Recurrence of Turbine Blade Cracks
Long-term Plant Safety Is Key Consideration
BERWICK, Pa., April 24, 2012 /PRNewswire/ -- A planned follow-up inspection of the Unit 1 main turbine at PPL's Susquehanna nuclear power plant in northeastern Pennsylvania revealed indications of cracks in blades that are similar to, but less extensive than, damage discovered and repaired in 2011.
Based on the inspection, PPL will replace one row of blades on the Unit 1 turbine during the current refueling and maintenance outage, and has decided as a precaution to shut down the Unit 2 reactor and inspect its main turbine after the Unit 1 outage is completed.
"Our number one objective, as always, is to operate the Susquehanna plant safely and reliably for the long term," said Timothy S. Rausch, PPL Susquehanna senior vice president and chief nuclear officer. "The decision to inspect the Unit 2 turbine is consistent with PPL's safety-driven approach to operating the plant."
The Unit 2 outage will be scheduled after Unit 1 resumes generating electricity, he said. The turbine blade replacement on Unit 1 will have a minimal effect on the duration of the current outage, which began March 31 and is expected to continue into mid-May.
The financial impact to PPL Corporation from the additional turbine work at the Susquehanna plant, including energy sales margins and repair costs, is not expected to be material.
PPL Corporation is maintaining its 2012 forecast of $2.15 to $2.45 per share in earnings from ongoing operations.
"Inspecting the main turbine was one of the key planned tasks during the Unit 1 outage," Rausch said. "Well before the outage began, we planned and prepared for the possibility that the turbine inspection would result in a decision to replace blades."
Diagnostic equipment installed on the turbines in 2011 has provided data about the possible causes of the problem. As part of the ongoing Unit 1 outage and the upcoming Unit 2 outage, PPL Susquehanna will install additional equipment that will, along with the analysis already conducted, be used to validate the suspected causes currently under engineering review.
"We will learn all we can about the causes so we can make adjustments to prevent future problems and share what we learn with others in the nuclear power industry," Rausch said.
The two units at the Susquehanna plant generate electricity by boiling water to make steam that passes through turbines, which have many rows of fanlike metal blades on rotating parts. The spinning blades turn a generator that produces electricity. The two units combined have a generating capacity of about 2,500 megawatts.
The Susquehanna plant is located in Luzerne County, Pa., about seven miles north of Berwick, and is owned jointly by PPL Susquehanna and Allegheny Electric Cooperative Inc., and operated by PPL Susquehanna.
PPL Susquehanna is one of PPL Corporation's generating facilities. Headquartered in Allentown, Pa., PPL Corporation (NYSE: PPL) owns or controls about 19,000 megawatts of generating capacity in the United States, sells energy in key U.S. markets and delivers electricity and natural gas to about 10 million customers in the United States and the United Kingdom. More information is available at www.pplsusquehanna.com.
"Earnings from ongoing operations" should not be considered as an alternative to reported earnings, or net income attributable to PPL, which is an indicator of operating performance determined in accordance with generally accepted accounting principles (GAAP). PPL believes that "earnings from ongoing operations," although a non-GAAP financial measure, is also useful and meaningful to investors because it provides management's view of PPL's fundamental earnings performance as another criterion in making investment decisions. PPL's management also uses "earnings from ongoing operations" in measuring certain corporate performance goals. Other companies may use different measures to present financial performance.
"Earnings from ongoing operations" is adjusted for the impact of special items. Special items include:
- Adjusted energy-related economic activity (as discussed below).
- Foreign currency-related economic hedges.
- Gains and losses on sales of assets not in the ordinary course of business.
- Impairment charges (including impairments of securities in the company's nuclear decommissioning trust funds).
- Workforce reduction and other restructuring impacts.
- Acquisition-related adjustments.
- Other charges or credits that are, in management's view, not reflective of the company's ongoing operations.
Adjusted energy-related economic activity includes the changes in fair value of positions used economically to hedge a portion of the economic value of PPL's generation assets, full-requirement sales contracts and retail activities. This economic value is subject to changes in fair value due to market price volatility of the input and output commodities (e.g., fuel and power) prior to the delivery period that was hedged. Also included in energy-related economic activity is the ineffective portion of qualifying cash flow hedges, the monetization of certain full-requirement sales contracts and premium amortization associated with options. This economic activity is deferred, with the exception of the full-requirement sales contracts that were monetized, and included in earnings from ongoing operations over the delivery period of the item that was hedged or upon realization. Management believes that adjusting for such amounts provides a better matching of earnings from ongoing operations to the actual amounts settled for PPL's underlying hedged assets. Please refer to the Notes to the Consolidated Financial Statements and MD&A in PPL Corporation's periodic filings with the Securities and Exchange Commission for additional information on energy-related economic activity.
Statements contained in this news release, including statements with respect to future earnings, cash flows, financing, regulation and corporate strategy are "forward-looking statements" within the meaning of the federal securities laws. Although PPL Corporation believes that the expectations and assumptions reflected in these forward-looking statements are reasonable, these statements are subject to a number of risks and uncertainties, and actual results may differ materially from the results discussed in the statements. The following are among the important factors that could cause actual results to differ materially from the forward-looking statements: market demand and prices for energy, capacity and fuel; weather conditions affecting customer energy usage and operating costs; competition in power markets; the effect of any business or industry restructuring; the profitability and liquidity of PPL Corporation and its subsidiaries; new accounting requirements or new interpretations or applications of existing requirements; operating performance of plants and other facilities; the length of scheduled and unscheduled outages at our plants; environmental conditions and requirements and the related costs of compliance, including environmental capital expenditures and emission allowance and other expenses; system conditions and operating costs; development of new projects, markets and technologies; performance of new ventures; asset or business acquisitions and dispositions, and PPL Corporation's ability to realize the expected benefits from acquired businesses, including the 2010 acquisition of Louisville Gas and Electric Company and Kentucky Utilities Company and the 2011 acquisition of the Central Networks electricity distribution businesses in the U.K.; any impact of hurricanes or other severe weather on our business, including any impact on fuel prices; receipt of necessary government permits, approvals, rate relief and regulatory cost recovery; capital market conditions and decisions regarding capital structure; the impact of state, federal or foreign investigations applicable to PPL Corporation and its subsidiaries; the outcome of litigation against PPL Corporation and its subsidiaries; stock price performance; the market prices of equity securities and the impact on pension income and resultant cash funding requirements for defined benefit pension plans; the securities and credit ratings of PPL Corporation and its subsidiaries; political, regulatory or economic conditions in states, regions or countries where PPL Corporation or its subsidiaries conduct business, including any potential effects of threatened or actual terrorism or war or other hostilities; foreign exchange rates; new state, federal or foreign legislation, including new tax legislation; and the commitments and liabilities of PPL Corporation and its subsidiaries. Any such forward-looking statements should be considered in light of such important factors and in conjunction with PPL Corporation's Form 10-K and other reports on file with the Securities and Exchange Commission.
SOURCE PPL Susquehanna
WANT YOUR COMPANY'S NEWS FEATURED ON PRNEWSWIRE.COM?
Newsrooms &
Influencers
Digital Media
Outlets
Journalists
Opted In
Share this article