Market Monitor Finds PJM Wholesale Electricity Markets Competitive
2019 State of the Market Report for PJM: January through March
EAGLEVILLE, Pa., May 9, 2019 /PRNewswire/ -- PJM Interconnection's wholesale electric energy market produced competitive results during the first three months of 2019, according to the 2019 State of the Market Report for PJM: January through March, released today by Monitoring Analytics, LLC, the Independent Market Monitor for PJM.
The Independent Market Monitor, Joseph Bowring, announced findings of the report today. The report is the Independent Market Monitor's assessment of the competitiveness of the wholesale electricity markets managed by PJM in 13 states and the District of Columbia. The report includes analysis of market structure, participant behavior and market performance for each of the PJM markets.
"Our analysis concludes that the results of the PJM Energy Market were competitive in the first three months of 2019," Bowring said.
Energy prices were significantly lower in the first three months of 2019 than in the first three months of 2018. The load-weighted average real-time LMP was 39.0 percent lower in the first three months of 2019 than in the first three months of 2018, $30.16 per MWh versus $49.45 per MWh. Of the $19.29 per MWh decrease, 40 percent was a result of lower fuel costs. The balance of the decrease was a result of decreased load, adjusted dispatch, and lower markups.
Energy prices in PJM in the first three months of 2019 were set, on average, by units operating at, or close to, their short run marginal costs, although this was not always the case. This is evidence of generally competitive behavior and competitive market outcomes, although high markups for some marginal units did affect prices.
Net revenue is a key measure of overall market performance as well as a measure of the incentive to invest in new generation to serve PJM markets. Net revenues are significantly affected by fuel prices, energy prices and capacity prices. In the first three months of 2019, average energy market net revenues decreased by 65 percent for a new CT, 42 percent for a new CC, 85 percent for a new coal plant, 37 percent for a new nuclear plant, 93 percent for a new diesel, 40 percent for a new on shore wind installation, 36 percent for a new off shore wind installation and 22 percent for a new solar installation compared to the first three months of 2018.
Total energy uplift charges decreased by $63.5 million or 76.6 percent, from $82.2 million in the first three months of 2018 to $19.4 million in the first three months of 2019.
Total payments for demand response programs increased by $28.4 million, 21.8 percent, from $130.2 million in the first three months of 2018 to $158.6 million in the first three months of 2019. The capacity market is the primary source of revenue to participants in PJM demand response programs. In the first three months of 2019, payments to demand response resources in the capacity market increased by $30.2 million, 23.8 percent, while payments to demand resources in the economic program decreased by $0.7 million or 75.2 percent.
When there are binding transmission constraints and locational price differences, load pays more for energy than generation is paid to produce that energy. The difference is congestion. Congestion costs decreased by $497.1 million or 75.2 percent, from $661.0 million in the first three months of 2018 to $163.9 million in the first three months of 2019. Congestion reflects the underlying characteristics of the power system, including the capability of transmission facilities, the fuel costs and geographic distribution of generation facilities and the geographic distribution of load.
ARR and FTR revenues offset 100.0 percent of total congestion costs for load during the 2016/2017 planning period but offset only 50.0 percent of total congestion costs for the 2017/2018 planning period, the first planning period in which new rules required the allocation of balancing congestion to load instead of FTR holders. ARR and FTR revenues offset 81.5 percent of total congestion costs for the first ten months of the 2018/2019 planning period, the first year ARR holders will receive surplus congestion revenue. The goal of the FTR market design should be to ensure that load has the rights to 100 percent of the congestion revenues.
The Independent Market Monitor (also known as the Market Monitoring Unit or MMU) evaluates the operation of PJM's wholesale markets to identify ineffective market rules and tariff provisions, proposes improvements to market rules and tariff provisions when needed, monitors compliance with and implementation of the market rules, identifies potential anticompetitive behavior by market participants and provides comprehensive market analysis critical for informed policy and decision making. Joseph Bowring, the Market Monitor, ensures the independence and objectivity of the monitoring program.
For a copy of the State of the Market Report, visit Monitoring Analytics at: http://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2019.shtml
SOURCE Monitoring Analytics, LLC