GULFPORT, Miss., Nov. 23, 2016 /PRNewswire/ -- Mississippi Power announced today it had achieved another major milestone with electricity generated in the second gasifier at the Kemper County energy facility by synthesis gas, or syngas, from lignite. Last month, the company announced electricity had been generated in the first of the facility's two gasifiers.
"This is a substantial step forward for the project," said Mississippi Power Chairman, President and CEO Anthony L. Wilson. "We are now closer to integrating all of the systems at the facility to deliver on our mission to provide clean, reliable energy for our customers. I cannot be happier with this step in the process."
The company announced earlier this month it was completing maintenance on the first gasifier at the plant, which followed six weeks of successful syngas production including generation of the plant's first electricity using syngas.
The remaining major milestones for the IGCC include successful carbon capture and integration of all systems necessary for both combustion turbines to simultaneously generate electricity with syngas. The expected date for the plant to be placed in service is Dec. 31.
About Mississippi Power
Mississippi Power, a subsidiary of Southern Company (NYSE: SO), produces safe, reliable and environmentally responsible energy for more than 186,000 customers in 23 southeast Mississippi counties. Mississippi Power earned the 2015 ReliabilityOneTM Award for outstanding midsize utility for excellence in storm restoration and recovery efforts as well as being a leader in reliability, customer service and safety. Visit our websites at mississippipower.com and mississippipowernews.com, like us on Facebook, and follow us on Twitter, LinkedIn, Google+ and YouTube.
Cautionary Note Regarding Forward-Looking Statements
Certain information contained in this communication is forward-looking information based on current expectations and plans that involve risks and uncertainties. Forward-looking information includes, among other things, statements concerning the projected schedule for completing construction and start-up of the integrated coal gasification combined cycle project in Kemper County, Mississippi (the Kemper IGCC). Mississippi Power cautions that there are certain factors that could cause actual results to differ materially from the forward-looking information that has been provided. The reader is cautioned not to put undue reliance on this forward-looking information, which is not a guarantee of future performance and is subject to a number of uncertainties and other factors, many of which are outside the control of Mississippi Power; accordingly, there can be no assurance that such suggested results will be realized. The following factors, in addition to those discussed in Mississippi Power's Annual Report on Form 10-K for the fiscal year ended December 31, 2015, and subsequent securities filings, could cause actual results to differ materially from management expectations as suggested by such forward-looking information: changes in tax and other laws and regulations to which Mississippi Power is subject as well as changes in application of existing laws and regulations; the ability to control costs and avoid cost overruns during the development and construction of facilities, which include the development and construction of generating facilities with designs that have not been finalized or previously constructed, including changes in labor costs and productivity, adverse weather conditions, shortages and inconsistent quality of equipment, materials, and labor, sustaining nitrogen supply, contractor or supplier delay, non-performance under operating or other agreements, operational readiness, including specialized operator training and required site safety programs, unforeseen engineering or design problems, start-up activities (including major equipment failure and system integration), and/or operational performance (including additional costs to satisfy any operational parameters ultimately adopted by the Mississippi Public Service Commission (PSC)); the ability to construct facilities in accordance with the requirements of permits and licenses, to satisfy any environmental performance standards and the requirements of tax credits and other incentives, and to integrate facilities into the Southern Company system upon completion of construction; advances in technology; actions related to cost recovery for the Kemper IGCC, including the ultimate impact of the 2015 decision of the Mississippi Supreme Court, the Mississippi PSC's December 2015 rate order, and related legal or regulatory proceedings, Mississippi PSC review of the prudence of Kemper IGCC costs and approval of further permanent rate recovery plans, actions relating to proposed securitization, satisfaction of requirements to utilize grants, and the ultimate impact of the termination of the proposed sale of an interest in the Kemper IGCC to South Mississippi Electric Power Association; and the ability of counterparties of Mississippi Power to make payments as and when due and to perform as required. Mississippi Power expressly disclaims any obligation to update any forward-looking information.
Logo - http://photos.prnewswire.com/prnh/20141211/163911LOGO
Logo - http://photos.prnewswire.com/prnh/20080801/SOCOLOGO
SOURCE Mississippi Power
Related Links
WANT YOUR COMPANY'S NEWS FEATURED ON PRNEWSWIRE.COM?
Newsrooms &
Influencers
Digital Media
Outlets
Journalists
Opted In
Share this article